Implementation Roadmap

Overview

The redesign is implemented in 9 phases, progressing from contract definition through schema migration, feature implementation, and legacy decommission. Each phase has defined scope, dependencies, and rollback points.


Phase Summary

Phase Scope Duration Dependencies
0 Contract Freeze — type definitions, Zod schemas, feature flags, test factories 1 week None
1 Schema & Runtime Foundation — Prisma migration, Competition/Round/JuryGroup CRUD 2 weeks Phase 0
2 Policy Engine — centralized context resolver, policy resolution, assignment policy evaluator 1 week Phase 1
3 Invite/Onboarding Integration — jury memberships on invite, assignment intent, onboarding routing 12 weeks Phase 1
4 Backend Orchestration — enhanced assignment, submission round manager, mentor workspace, deliberation service 2 weeks Phase 2, 3
5 Admin Control Plane + Participant UX — competition wizard, round management, jury/applicant/mentor dashboards 2 weeks Phase 4
6 Special Awards + Live Finals + Deliberation — award modes, stage manager, deliberation voting UI 2 weeks Phase 4, 5
7 Platform-Wide Refit — remove Pipeline/Track/Stage references, drop old tables 2 weeks Phase 5, 6
8 Cutover & Legacy Decommission — enable new contracts, deprecate legacy, burn-in period 1 week Phase 7

Total estimated duration: 1415 weeks


Dependency Graph

Phase 0 ──→ Phase 1 ──→ Phase 2 ──→ Phase 4 ──→ Phase 5 ──→ Phase 7 ──→ Phase 8
                    └──→ Phase 3 ──┘        └──→ Phase 6 ──┘
  • Phases 2 and 3 can run in parallel after Phase 1
  • Phase 4 requires both Phase 2 and 3
  • Phases 5 and 6 can partially overlap
  • Phase 7 requires both Phase 5 and 6

Critical path: 0 → 1 → 2 → 4 → 5 → 7 → 8 (12 weeks minimum)


Phase Details

Phase 0: Contract Freeze (1 week)

Goal: Lock down all type definitions, schemas, and interfaces before any implementation begins.

Deliverables:

  • All Prisma model definitions finalized (see 02-data-model.md)
  • All 7 Zod config schemas finalized (IntakeConfig through DeliberationConfig)
  • All new enum definitions finalized
  • Feature flag infrastructure in place
  • Test factory functions for all new models
  • TypeScript type exports for all new models

Rollback: No production changes. Delete type files if needed.

Gate: All type definitions reviewed and approved. No changes to schemas after this phase without architecture sign-off (see "No Silent Contract Drift" in 13-open-questions-and-governance.md).


Phase 1: Schema & Runtime Foundation (2 weeks)

Goal: New database tables exist alongside old ones. Basic CRUD operations work.

Deliverables:

  • Prisma migration: add Competition, Round, JuryGroup, JuryGroupMember, SubmissionWindow, SubmissionFileRequirement, DeliberationSession, DeliberationVote, DeliberationResult, DeliberationParticipant, ResultLock, ResultUnlockEvent, MentorMessage, AssignmentIntent, AssignmentException, SubmissionPromotionEvent tables
  • New enums: RoundType, RoundStatus, CompetitionStatus, CapMode, DeadlinePolicy, DeliberationMode, DeliberationStatus, TieBreakMethod, etc.
  • Basic tRPC routers: competition.create, competition.getById, round.create, juryGroup.create, juryGroup.addMember
  • Admin can create a Competition with Rounds through the API (no UI yet)

Rollback: Drop new tables. No old tables modified.

Gate: All new tables exist with correct schemas. CRUD operations pass integration tests.


Phase 2: Policy Engine (1 week)

Goal: Centralized resolution of competition context and assignment policies.

Deliverables:

  • CompetitionContextResolver service: given a roundId, returns the full competition context (competition, round type, config, jury group, submission windows, etc.)
  • Policy resolution function: 5-layer precedence chain for assignment caps, ratios, and modes
  • Assignment policy evaluator: canAssignMore(member), getEffectiveCap(member), getRemainingCapacity(member)
  • Unit tests for all policy combinations

Rollback: Remove new services. No data changes.

Gate: Policy resolution returns correct values for all 5 layers. Edge cases (null overrides, conflicting settings) handled correctly.


Phase 3: Invite/Onboarding Integration (12 weeks)

Goal: Jury memberships are created at invite time. Judges can self-service during onboarding.

Deliverables:

  • Invite flow creates JuryGroupMember record when judge is invited to a jury
  • AssignmentIntent records can be created during invite (pre-assignment)
  • Onboarding page shows cap/ratio preferences when allowOnboardingSelfService is true
  • Judge can adjust cap and category bias during onboarding
  • Admin can review and override self-service values

Rollback: Revert invite flow changes. JuryGroupMember records can be deleted.

Gate: End-to-end flow: invite judge → judge accepts → onboarding shows jury details → judge adjusts preferences → admin sees updated values.


Phase 4: Backend Orchestration (2 weeks)

Goal: All backend services for the 8-round flow are operational.

Deliverables:

  • RoundEngine service: state machine for round transitions (replaces StageEngine)
  • Enhanced Assignment service: hard/soft cap algorithm, category bias, unassigned queue, COI check
  • SubmissionRoundManager: manages submission windows, file requirements, read-only enforcement
  • MentorWorkspaceService: messaging, file upload, file comments, file promotion
  • DeliberationService: session creation, vote submission, aggregation (Borda count / vote tally), tie-breaking, result lock
  • AI Shortlist service: generates ranked recommendations at end of evaluation rounds
  • ResultLockService: lock/unlock with audit trail

Rollback: Remove new services. Feature flags prevent activation.

Gate: All services pass unit tests. Integration test covers full R1→R8 flow with test data.


Phase 5: Admin Control Plane + Participant UX (2 weeks)

Goal: Admin can configure and run a competition through the UI. Participants see the correct experience.

Deliverables:

  • Competition Wizard: create competition with rounds, configure each round type
  • Round Management: view/edit round configs, manage submission windows, set deadlines
  • Juries Management (NEW section): create JuryGroups, add/remove members, configure caps/ratios, view assignments
  • Assignment Dashboard: view assignments, manage unassigned queue, manual override
  • Jury Dashboard: countdown, assigned projects, multi-round doc viewing, scoring/feedback
  • Applicant Portal: multi-round doc upload, read-only enforcement, submission status
  • Mentor Dashboard: assigned teams, messaging, file management, promotion

Rollback: Revert UI pages. Backend services still work via API.

Gate: Admin can create, configure, and manage a full competition through the UI. Jury, applicant, and mentor dashboards functional.


Phase 6: Special Awards + Live Finals + Deliberation (2 weeks)

Goal: The most complex runtime features are operational.

Deliverables:

  • Special Awards: create awards with routing modes, eligibility filtering, per-award jury, doc requirements, review windows, single-judge mode
  • Live Finals Stage Manager: admin controls for ceremony flow, project cursor, voting windows
  • Jury 3 Live Interface: real-time notes, all docs from prior rounds, prior jury data (if enabled), live scoring
  • Audience Voting: optional per-category audience vote, reveal timing configuration
  • Deliberation UI: session management, juror voting interface (both modes), result display, tie-breaking, admin lock
  • Result Lock: admin locks results, unlock requires super-admin with reason

Rollback: Feature flags disable awards, live finals, and deliberation. Fall back to basic flow.

Gate: Full live finals ceremony simulation. Deliberation voting in both modes. Result lock and unlock. Award creation and selection.


Phase 7: Platform-Wide Refit (2 weeks)

Goal: Remove all references to Pipeline, Track, and Stage from the codebase. Estimated 120+ files, ~350 hours of work.

Sub-phases (ordered by dependency):

Sub-Phase Scope Files Est. Hours
7a Database: rename FKs (stageId→roundId) in AudienceVote, COIDeclaration, ProjectStatusHistory, DigestLog, PartnerAccess 1 (schema) + migration 8
7b Types & libraries: rewrite pipeline-wizard.ts, wizard-config.ts, pipeline-defaults.ts, pipeline-validation.ts, stage-config-schema.ts 6 32
7c Core routers: rename pipeline.ts→competition.ts, stage.ts→round.ts, track.ts→(delete), stageAssignment.ts→roundAssignment.ts 4 24
7d Dependent routers: update all 20 routers with stageId/pipelineId references (evaluation, file, live, invite, notification, etc.) 20 80
7e Services: rename stage-engine→round-engine, stage-filtering→round-filtering, stage-assignment→round-assignment, stage-notifications→round-notifications, live-control (update refs) 11 50
7f Admin pages: rename 35+ pages referencing pipeline/stage, update breadcrumbs, wizard, config editors 35+ 52
7g Jury pages: update 16 jury pages + components (stage routes→round routes, assignment queries, evaluation forms) 16 18
7h Applicant pages: update 8 pages (pipeline visualization→competition progress, stage documents→round documents) 8 12
7i Infrastructure: update Docker entrypoint, cron jobs, webhook event names, notification templates, seed data 4 11
7j Tests: update 13+ test files + helpers.ts, rename factories, update all assertions 13+ 45

Week 1: Sub-phases 7a7e (database, types, routers, services — backend foundation) Week 2: Sub-phases 7f7j (UI pages, infrastructure, tests — frontend + verification)

Deliverables:

  • All pipeline references renamed to competition in routers, services, types, UI
  • All stage references renamed to round
  • All track references removed
  • All imports, type aliases, and variable names updated
  • Old database tables dropped (Pipeline, Track, Stage, ProjectStageState)
  • Seed data updated to use new models
  • All background jobs and webhook events using new names

Rollback: This is the point of no return for the old schema. Rollback requires restoring from backup.

Gate: grep -r "pipeline\|Pipeline\|stage\|Stage\|track\|Track" src/ returns zero results (excluding legitimate uses like "stage manager" in live finals). All tests pass. Build succeeds.


Phase 8: Cutover & Legacy Decommission (1 week)

Goal: Production system running entirely on the new architecture.

Deliverables:

  • Feature flags set to new system for all subsystems
  • Legacy API endpoints deprecated (return 410 Gone with migration guide)
  • Burn-in period: monitor for errors, performance regressions
  • Documentation updated (CLAUDE.md, README, API docs)
  • Seed data updated
  • Docker entrypoint updated for new migration flow

Rollback: Feature flags can revert to legacy for individual subsystems (only if old tables still exist, i.e., Phase 7 wasn't completed).

Gate: 72-hour burn-in with zero critical errors. All release gates AF passed (see 12-observability-and-release-gates.md).


Rollback Strategy

Phase Rollback Method Data Loss Risk
0 Delete type files None
1 Drop new tables None (old tables untouched)
2 Remove services None
3 Revert invite flow JuryGroupMember records deleted
4 Feature flag off None
5 Revert UI pages None
6 Feature flag off None
7 Point of no return — restore from backup Requires backup
8 Feature flags to legacy Only if Phase 7 not completed

Risk Mitigation

Risk Mitigation
Schema migration breaks existing data Phase 1 adds tables alongside old ones. No modifications to existing tables until Phase 7.
Assignment algorithm incorrect Extensive unit tests in Phase 2. Manual override always available.
Deliberation edge cases Phase 6 includes deliberation test matrix (see 11-testing-and-qa.md).
Live finals concurrency Load testing in Phase 6. See 12-observability-and-release-gates.md.
Late requirement changes "No Silent Contract Drift" policy enforced after Phase 0.