05. Estimated Timelines

1. Date Anchors

  • Planning baseline date: Thursday, February 26, 2026
  • Proposed execution start: Monday, March 2, 2026
  • 12-week target launch window end: Sunday, May 24, 2026
  • Recommended contingency buffer: May 25-31, 2026

2. Timeline Summary

Phase Dates Duration Confidence
Phase 0 prerequisites Mar 2 - Mar 8 1 week High
Phase 1 safety substrate Mar 9 - Mar 22 2 weeks Medium
Phase 2 Hub APIs/models Mar 16 - Mar 29 2 weeks (overlap) High
Phase 3 wrapper execution layer Mar 23 - Apr 12 3 weeks Medium
Phase 4 provisioner retool Mar 30 - Apr 19 3 weeks (overlap) Medium
Phase 5 mobile + website + portal Apr 6 - May 3 4 weeks Medium
Phase 6 templates + demo Apr 27 - May 10 2 weeks Medium
Phase 7 hardening + canary + launch May 4 - May 24 3 weeks Medium-Low

3. Milestones

Milestone Target Date Exit Condition
M1: Cleanup gate passed Mar 8, 2026 n8n and deprecated deploy paths removed; plaintext secret leak fixed
M2: Security substrate alpha Mar 22, 2026 redaction proxy + classifier + plugin skeleton integrated
M3: Hub tenant APIs beta Mar 29, 2026 register/heartbeat/approval/usage contracts stable
M4: First full tenant provision Apr 12, 2026 new VPS boots with OpenClaw + Safety + heartbeat
M5: Customer interface beta May 3, 2026 web portal + mobile approvals + onboarding flow functional
M6: Launch candidate May 17, 2026 full security/perf test pass; canary starts
M7: Founding member launch May 24, 2026 canary complete; runbooks and rollback drills signed off

4. Weekly View (Condensed)

Week 1  (Mar 2)   : Phase 0 prerequisite cleanup
Week 2-3          : Phase 1 safety substrate begins
Week 3-4          : Phase 2 Hub API/data model work (parallel)
Week 4-6          : Phase 3 wrapper execution + adapters
Week 5-7          : Phase 4 provisioner retool and browser migration
Week 6-9          : Phase 5 customer portal/mobile/website
Week 9-10         : Phase 6 templates + interactive demo
Week 10-12        : Phase 7 hardening, canary rollout, launch
Buffer Week       : May 25-31 contingency

5. Critical Timeline Risks

Risk Schedule Impact If Realized
OpenClaw hook behavior drift or undocumented edge cases +1 to +2 weeks
Provisioner migration instability on fresh VPS images +1 week
Mobile push approval reliability issues (iOS/Android differences) +0.5 to +1 week
Token billing reconciliation defects with Stripe meter events +1 week
Security findings in redaction/gating late in cycle +1 to +3 weeks

6. Confidence Ranges

Scenario Launch Window
Optimistic May 17-24, 2026
Most likely May 24-31, 2026
Conservative June 7-14, 2026

7. Scope Compression Options (If Needed)

To preserve security and launch by May 24-31, de-scope in this order:

  1. Delay WhatsApp/Telegram fallback to post-launch.
  2. Limit initial tool adapter set to top 8 usage tools, keep others on browser fallback.
  3. Ship 3 first-hour templates at launch, add the 4th in first patch.

Do not cut redaction, gating, approval, or metering correctness work.