# Release Runbook (Atomic Cutover) ## Preconditions - all prior phase gates complete - signed release checklist - rollback owner and communication owner assigned ## Cutover Sequence 1. freeze non-release writes and announce maintenance window 2. execute final backup snapshot 3. deploy release candidate build 4. run reset/reseed as planned for production state model 5. run post-deploy integrity and smoke checks 6. run mandatory critical-path E2E subset 7. publish completion and monitor ## Immediate Post-Cutover Checks - auth and role gating paths - transition mutation sanity - assignment preview/execute path - live cursor operations - audience vote acceptance and dedupe - reporting endpoint correctness ## Rollback Trigger Conditions - integrity check failures - critical mutation path failure - unacceptable error-rate spike ## Rollback Plan (High Level) - restore backup snapshot - redeploy previous stable build - validate critical-path smoke tests - issue incident communication and postmortem schedule