# 05. Estimated Timelines ## 1. Date Anchors - Planning baseline date: **Thursday, February 26, 2026** - Proposed execution start: **Monday, March 2, 2026** - 12-week target launch window end: **Sunday, May 24, 2026** - Recommended contingency buffer: **May 25-31, 2026** ## 2. Timeline Summary | Phase | Dates | Duration | Confidence | |---|---|---:|---| | Phase 0 prerequisites | Mar 2 - Mar 8 | 1 week | High | | Phase 1 safety substrate | Mar 9 - Mar 22 | 2 weeks | Medium | | Phase 2 Hub APIs/models | Mar 16 - Mar 29 | 2 weeks (overlap) | High | | Phase 3 wrapper execution layer | Mar 23 - Apr 12 | 3 weeks | Medium | | Phase 4 provisioner retool | Mar 30 - Apr 19 | 3 weeks (overlap) | Medium | | Phase 5 mobile + website + portal | Apr 6 - May 3 | 4 weeks | Medium | | Phase 6 templates + demo | Apr 27 - May 10 | 2 weeks | Medium | | Phase 7 hardening + canary + launch | May 4 - May 24 | 3 weeks | Medium-Low | ## 3. Milestones | Milestone | Target Date | Exit Condition | |---|---|---| | M1: Cleanup gate passed | Mar 8, 2026 | n8n and deprecated deploy paths removed; plaintext secret leak fixed | | M2: Security substrate alpha | Mar 22, 2026 | redaction proxy + classifier + plugin skeleton integrated | | M3: Hub tenant APIs beta | Mar 29, 2026 | register/heartbeat/approval/usage contracts stable | | M4: First full tenant provision | Apr 12, 2026 | new VPS boots with OpenClaw + Safety + heartbeat | | M5: Customer interface beta | May 3, 2026 | web portal + mobile approvals + onboarding flow functional | | M6: Launch candidate | May 17, 2026 | full security/perf test pass; canary starts | | M7: Founding member launch | May 24, 2026 | canary complete; runbooks and rollback drills signed off | ## 4. Weekly View (Condensed) ```text Week 1 (Mar 2) : Phase 0 prerequisite cleanup Week 2-3 : Phase 1 safety substrate begins Week 3-4 : Phase 2 Hub API/data model work (parallel) Week 4-6 : Phase 3 wrapper execution + adapters Week 5-7 : Phase 4 provisioner retool and browser migration Week 6-9 : Phase 5 customer portal/mobile/website Week 9-10 : Phase 6 templates + interactive demo Week 10-12 : Phase 7 hardening, canary rollout, launch Buffer Week : May 25-31 contingency ``` ## 5. Critical Timeline Risks | Risk | Schedule Impact If Realized | |---|---| | OpenClaw hook behavior drift or undocumented edge cases | +1 to +2 weeks | | Provisioner migration instability on fresh VPS images | +1 week | | Mobile push approval reliability issues (iOS/Android differences) | +0.5 to +1 week | | Token billing reconciliation defects with Stripe meter events | +1 week | | Security findings in redaction/gating late in cycle | +1 to +3 weeks | ## 6. Confidence Ranges | Scenario | Launch Window | |---|---| | Optimistic | May 17-24, 2026 | | Most likely | May 24-31, 2026 | | Conservative | June 7-14, 2026 | ## 7. Scope Compression Options (If Needed) To preserve security and launch by May 24-31, de-scope in this order: 1. Delay WhatsApp/Telegram fallback to post-launch. 2. Limit initial tool adapter set to top 8 usage tools, keep others on browser fallback. 3. Ship 3 first-hour templates at launch, add the 4th in first patch. Do **not** cut redaction, gating, approval, or metering correctness work.